The following are required to activate the connection of the photovoltaic self-consumption system:
- Submission of a request by the interested party declaring that their installation is ready, accompanied by the relevant supporting documents required at this stage.
- Completion of the work required by HEDNO, such as replacing the existing meter, carrying out any connection works, and conducting the required inspections of the generation installation to ensure its safe connection to the Network.