The “Photovoltaics on the Roof” Program, hereinafter the “Program,” subsidizes households for the installation of PV systems with energy storage, and farmers for the installation of PV systems with or without energy storage for self-consumption under an energy netting scheme.

Complete guide to applying for the “Photovoltaics on the Roof” program
HELLENIC REPUBLIC

MINISTRY OF ENVIRONMENT AND ENERGY

PROGRAM IMPLEMENTATION GUIDE - “Photovoltaics on the Roof”

GUIDE CONTENTS

1. Scope and Objective of the Action 

2. Action Budget – Source of Funding

3. Beneficiary Categories – Eligible Applicants 

3.1Beneficiary Categories

3.2Application Submission Requirements 

3.3Program Requirements – Specifications

3.4Type and Amount of Grant

3.5Eligible Expenditures

4. Action Implementation Procedures

5. Stakeholders

6. Program Implementation Deadlines 

6.1Start of Eligibility

6.2Submission of Grant Application

6.3Evaluation of Funding Applications

6.4 Program Implementation Period - Milestones and Deadlines 

7. Certification of the Subsidized Installation - Payment of the Grant

7.1Required Supporting Documents

7.2Grant Certification and Payment Procedure

7.3Issuance of Invoices - Payment

8. Beneficiaries’ Obligations

9. Consequences of Failure to Comply with Obligations 

10. Publicity and Information Activities

11. Personal Data Protection 



1. Scope and Objective of the Action 

The “Photovoltaics on the Roof” Program, hereinafter the “Program,” provides grants to households for the installation of PV systems with energy storage systems, and to farmers for the installation of PV systems with or without energy storage systems, for self-consumption using net metering.

In particular, the Program covers: 

  • Photovoltaic systems for generating electricity, with or without feeding electricity into the Grid, combined with an electricity storage system,

which are installed by self-consumers for net metering in accordance with Article 14A of Law 3468/2006 (Government Gazette A’ 129) on buildings (on the roof slab or roof of a building, including veranda canopies, pergolas, façades and awnings, as defined in Articles 16 and 19 of Law 4067/2012, as in force, as well as ancillary spaces of the building, such as storage rooms and parking spaces, as defined in paragraph 96 of Article 2 of the same law) or on the ground.

The Program covers the entire country and is expected to deliver significant benefits both to the beneficiaries and to the national economy as a whole. 

A strategic objective  is for the energy and climate targets set within the framework of the National Energy and Climate Plan (NECP) to contribute decisively to the necessary energy transition in the most economically competitive manner for the national economy, and to achieve a drastic reduction in greenhouse gas emissions through integrated and coherent programs of measures and policies. 

Given that buildings are currently responsible for approximately 40% of energy consumption, reducing energy consumption in buildings requires increased use of energy-efficient and low-emission heating systems, as well as the renovation or construction of smarter buildings using improved materials, in full accordance with the principles of the circular economy, with parallel  use of renewable energy technologies to meet heating and cooling needs, distributed generation systems through self-consumption schemes to meet buildings’ electricity needs and energy netting, as well as storage systems, including by strengthening the role of consumers.

Improving the energy efficiency of the country’s building stock is a key priority of the National Energy and Climate Plan, facilitating the cost-effective transformation of existing buildings into nearly zero-energy buildings while also aiming for a highly energy-efficient, decarbonized building stock by 2050.

Regarding the agricultural sector, the high potential is harnessed on the basis of the measures and policies provided for in the NECP, contributing to the reduction of greenhouse gas emissions, the promotion of renewable energy sources and the improvement of energy efficiency.

The Program aims to install self-consumption photovoltaic power stations in combination with electrical storage systems (batteries), which contribute to energy savings, help bring the building stock closer to the 2050 nearly zero-energy consumption standards, and reduce the cost of living.


2. Action Budget – Funding Source

The Action’s budget, in terms of Public Expenditure for subsidizing the installation of photovoltaic systems and storage systems, amounts to 200.000.000 €. 

The Program is included among the flagship projects for which public expenditure is funded by the Recovery and Resilience Facility. 

The allocation of Public Expenditure across the beneficiary categories is presented in the following table:

Expenditure Allocation Table

Category | Beneficiaries | Action | Budget (€)
A | Residential installations (Vulnerable Households) | Installation of a PV station with a storage system | 35.000.000€
B | Residential installations (Individual Income <=20.000€or Household Income <=40.000€) | Installation of a PV station with a storage system | 85.000.000€
C | Residential installations (Individual Income > 20.000€ or Household Income > 40.000€) | Installation of a PV station with a storage system | 50.000.000€
D | Farmers | Installation of a PV station with or without a storage system | 30.000.000€
Total Budget |  200.000.000€

For the inclusion of each application, the applicant’s electricity supply point is taken into account. This is also indicated in the Connection Agreement already concluded between the applicant and HEDNO.

Beneficiaries are required to certify and ensure the accuracy of the information they submit.


3. Beneficiary Categories – Eligible Applicants 

3.1 Beneficiary Categories

Individuals (households) and farmers (professional farmers or farmers under the special tax regime) who have already concluded a relevant Connection Agreement with HEDNO are eligible to participate in the Program. 

A condition for the photovoltaic system and the storage system (if applicable) to be included in the Program is that they have not received public aid from any other funding program. 

For Categories A, B and C, the photovoltaic station must be combined with a storage system, while beneficiaries  in Category D (Farmers) may choose whether or not to combine the photovoltaic station with a storage system.


3.2 Application Requirements 

An application must be submitted by the individual (household) or farmer identified as the counterparty to HEDNO in the Connection Agreement, which has already been concluded with HEDNO for the development of the photovoltaic station and storage system in question.

To submit an application, a beneficiary must:

  • have a Tax Identification Number and valid credentials for the online services of the Independent Authority for Public Revenue (AADE), through which their identity is verified, 

  • In the In the case of natural persons (households), except for Category A, they must have filed an income tax return for tax year 2021 (E1), either as the TAXPAYER on an individual or joint return, or indirectly as the “SPOUSE/SSP” on a joint return. The relevant return must have been assessed.

  • In the case of farmers, they must be registered in the Register of Farmers and Agricultural Holdings.

Clarification of special cases:

  • Applicants who filed an income tax return for the reference year (2021) as residents abroad are not eligible. 

  • Applicants who filed a joint income tax return in the reference year (2021) (specifically, as Taxpayer and Spouse/SSP) are not eligible if the other member or dependent child included on the return was a resident abroad in the aforementioned reference year (2021). 

  • Dependent members who do not file a separate return (i.e. are not required to file their own individual return) cannot apply to participate in the Program.

  • Eligible applicants in Category A (Vulnerable Households) are beneficiaries of the Social Residential Tariff at the time of application, according to the Register of Vulnerable Customers maintained by DEDDIE.

  • Eligible applicants in Category D (Farmers) are exclusively professional farmers and farmers under the special tax regime.

Important notes:

  • Each natural person (household) may submit only one application, for only one property, provided that all of the following conditions are met: 

    • It is the applicant’s primary or secondary residence (owned, rented, or granted for use). 

    • It has an active residential (and non-shared) electricity supply, which is used to verify the applicant’s residence.

  • For Category A (Vulnerable Households), the applicant may apply only for the electricity supply for which they have declared and are entitled to the Social Residential Tariff. If the applicant wishes to apply for a different supply, they do not qualify for Category A (Vulnerable Households), but may qualify for Category B or C. 

  • For Category D (Farmers), the applicant may submit only one application, for only one active agricultural-use electricity supply listed in the Register maintained by DEDDIE, which is also used to verify the applicant’s identity.

  • If an application is submitted for an agricultural electricity supply, the applicant is also permitted to apply for their residence.

  • More than one application for the same residence or agricultural-use electricity supply may not be submitted by different applicants.

  • If an application is rejected or cancelled, a new application may be submitted, provided that funds are available in the relevant category.

  • An applicant may not cancel an application more than two (2) times.


3.3 Program requirements and specifications

Photovoltaic systems 

The systems must be installed in accordance with Ministerial Decision ΥΑ ΥΠΕΝ/ΔΑΠΕΕΚ/15084/382 (Government Gazette, Series B, 759/2019), as in force, and must either be fixed mounting systems or ground-mounted solar tracking systems.

The maximum eligible installed capacity of the photovoltaic systems per installation funded under the Program is set at 10,8kW. 

Storage systems 

The storage system must have a minimum installed capacity equal to the photovoltaic station’s installed generation capacity for one hour. 

The maximum eligible capacity of the storage system per installation under the Program is set at 10,8kWh.

Operation of a photovoltaic station with a storage system

Management of storage systems (batteries) is intended to maximize self-consumption of the energy generated by the PV station. 

During operation of the system (PV with battery), the energy generated by the PV station is primarily supplied to consumption of the beneficiary. Any surplus production is directed to the storage system until it is full, and only once this has occurred may the available energy from the PV system be fed into the Grid. 

During periods when the energy produced by the PV plant is insufficient to cover the beneficiary’s consumption, this is covered primarily by discharging the storage system and secondarily by drawing energy from the Grid.

Compliance with the above operating requirements is ensured by the control system of the PV plant–battery system during the first five (5) years from the plant’s commissioning.


3.4 Type and amount of grant

The Programme provides a grant for a percentage (%) of the cost of the photovoltaic plant and the storage system, subject to the maximum grant amounts for the photovoltaic plant and the storage system, as specified in the following tables:


Table 1: Grant Rates for PV Plant and Battery

Category | Beneficiaries | PV Plant Grant Rate (€/kW) | Battery Grant Rate (€/kWh)
Capacity ≤ 5kWp | 5kWp <Capacity≤ 10,8kWp | Capacity ≤ 5kWh | 5kWh <Capacity≤10,8kWh
A | Residential installations (Vulnerable Households) | 65% | 60% | 100% | 100%
B  | Residential installations (Individual Income <= 20,000€ or Household Income <= 40.000€)  | 35% | 25% | 100% | 100%
C  | Residential installations (Individual Income > 20,000€ or Household Income > 40.000€) | 30% | 20% | 90% | 90%
D | Farmers | 40% | 40% | 90% | 90%


Table 2: Maximum Grant Amounts for PV Plant and Battery

Category | Beneficiaries | Maximum Grant Amount for PV Plant (€/kW) | Maximum Grant Amount for Battery (€/kWh)
Capacity ≤ 5kWp | 5kWp <Capacity≤ 10,8kWp | Capacity ≤ 5kWh | 5kWh <Capacity≤10,8kWh
A | Residential installations (Vulnerable Households) | 1.200€/kWp | 830€/kWp | 890€/kWh | 820€/kWh
B  | Residential installations (Individual Income <= 20,000€ or Household Income <= 40.000€)  | 650€/kWp | 350€/kWp | 890€/kWh | 820€/kWh
C  | Residential installations (Individual Income > 20,000€ or Household Income > 40.000€)  | 560€/kWp | 280€/kWp | 800€/kWh | 750€/kWh
D | Farmers | 450€/kWp | 450€/kWp | 600€/kWh | 600€/kWh

The above amounts include VAT (24%), which is an eligible expense under the Programme. If contractors/suppliers are subject to a reduced VAT rate or are exempt from the obligation to file a tax return and pay tax, the maximum grant amounts will be calculated on the basis of the net value plus the applicable VAT percentage (%). The initial cost excluding VAT (24%) is considered the basis for calculating the grant. For Category D (Farmers), the above amounts do not include VAT (24%), and therefore VAT is not an eligible expense under the Programme.

 If the applicant belongs to a category of persons with disabilities (PwD) with a disability rating of at least 67%, or to a single-parent family or a large family, the above rates and the maximum grant amounts for each category are increased by 10%, regardless of whether the applicant belongs to one or more of these categories. In any case, grant rates may not exceed 100%.


3.5 Eligible Expenses

The eligible expenses under this Programme are as follows:

  • Supply and installation of PV panels, an inverter, and ancillary materials (panels, cables, etc.)
  • Supply and installation of a mounting system.
  • Supply and installation of a PV meter.
  • Supply and installation of a storage system and ancillary materials (panels, cables, etc.)
  • Fee for system design and sizing (Photovoltaic system and battery) and installation works thereof.

Under this Program, costs are considered eligible, provided that they:

  • are necessary for implementing the physical scope,
  • are incurred within the eligible time period,
  • are lawful and regular,
  • are carried out in accordance with the principle of sound financial management 
  • are supported by the necessary supporting documents and records, as 
  • provided for under the applicable tax legislation, and are properly recorded in the accounts.

It is emphasized that:

  • VAT is an eligible cost (except for category D),
  • for rented/donated-use residences, the provisions of Commission Regulation 1407/2013 of the EU on de minimis aid apply, which set the cumulation limits (200.000 €). The beneficiary (full owner, usufructuary) must submit a declaration of compliance with the de minimis regulation, as amended from time to time, as well as the corresponding declarations of the other co-owners,
  • if costs exceed the maximum grant amounts, the excess cost must be covered by the beneficiary’s own contribution. 
  • It is emphasized that the station must not have been connected or activated before the application to participate in the Program is submitted.

4. Procedures for implementing the Program 

The process for installing the photovoltaic station and storage system by self-consumers under an energy netting arrangement is carried out pursuant to Ministerial Decision No. ΥΠΕΝ/ΔΑΠΕΕΚ/15084/382 (Government Gazette B 759/2019), as in force.

The review of the station’s technical connection criteria, the assessment of the connection request, and the conclusion of a connection agreement take place before the application to participate in the Program is submitted.

Installation of the station and conclusion of an energy netting agreement may proceed in parallel with the application to participate in the Program.

The time limits for installing the station are set out in the Connection Agreement concluded by the applicant self-consumer with DEDDIE.

The application to participate in the Program must be submitted before the station is connected and activated.


5. Bodies Involved

The Program Management and Implementation Body is Δ.Ε.Δ.Δ.Η.Ε. Α.Ε., which is responsible for:

  • designing the Program procedures 
  • receiving funding applications,
  • checking and evaluating applications
  • enrolling beneficiaries in the Program,
  • handling objections to submitted Program applications,
  • conducting systemic and sample-based checks to certify compliance with the terms and conditions of the Program
  • the reliability of the information and data declared and maintained, 
  • carrying out information and publicity activities throughout the duration of the Program,
  • managing, operating, and maintaining the Program website and Digital Platform,
  • organizing and operating a Help Desk for the Program,
  • monitoring the physical and financial scope of the Program, conducting administrative verifications, and carrying out systemic and sample-based checks,
  • conducting sample-based checks to confirm the existence of an electricity storage system (if applicable) and the use of wiring that ensures that generation from the PV station is directed, in order of priority, to cover the beneficiary’s electricity consumption, charge the battery of the RES system, and then flow to the Grid.
  • managing the relevant procedures for clearing and making Program payments,
  • monitoring and preparing the final report on the Program

To carry out specific tasks relating to verifications and checks, the approval of suppliers and products, the clearing of transactions, and any related management procedure, the Body may establish working groups and assign evaluation and checking tasks to  staff/associates who are members of those groups. 

Specifically, for the examination of objections that may be submitted, as applicable, by beneficiaries and At the successive stages of the Programme, a three-member Appeals Committee is appointed by decision of the Entity to handle objections from contractors/suppliers. The Committee rules on the objections submitted and submits its recommendations in writing to the competent body of the Entity, which takes the final decisions. The Committee is supported in its work by the working groups referred to in the previous paragraph.


6. Implementation Deadlines for the Action 

6.1 Eligibility start date

All projects and related expenses are eligible, irrespective of the date on which the Connection Agreement was concluded and the supporting documents in section 7.3 were issued, provided that the station has not been connected or activated before the application to participate in the Programme is submitted.

6.2Submission of a grant application

Prospective beneficiaries wishing to participate in the Programme shall submit a funding application through the appropriate electronic platform of DEDDIE S.A.

To submit the application, applicants must first authenticate using their personal credentials for the General Secretariat for Information Systems of Public Administration of the Ministry of Digital Governance (taxisnet), in accordance with Article   of Law No. 24/4727 (Government Gazette A’ 2020).184

After authenticating, the applicant creates the application and then submits it by providing:

  • the 11-digit electricity supply number to which the photovoltaic station will be connected , with a storage system if applicable (completed automatically),
  • the capacity of the photovoltaic station and storage system, if applicable (completed automatically),
  • the capacity of the storage system, if applicable. The maximum capacity that may be entered is 50kWh,
  • the category under which the applicant falls and for which they are seeking a grant, and whether they are a person with a disability (PWD) with a disability rating of at least 67%, or belong to a single-parent or large family, 
  • their individual or family income. This is not required for eligible applicants in Category A (Vulnerable Households) and Category D (Farmers),
  • the Connection Agreement already concluded by the applicant with DEDDIE,
  • a unique email address, which will be verified by sending a one-time code and will be used if the funding application is approved, as well as for all related communication with the beneficiary,
  • the beneficiary’s or spouse’s income tax clearance statement and those of family members who are dependants (in the case of separate tax returns). This document is not required for eligible applicants in Category A (Vulnerable Households) and Category D (Farmers),
  • a de minimis declaration in the case of a rented or rent-free residence. This document is not required for eligible applicants in Category D (Farmers),
  • a certificate of professional farmer status or proof of registration as a farmer under the special regime, for eligible applicants in Category D (Farmers),
  • a Disability Certification Result Notification issued by the Disability Certification Centre, or, as applicable, a document from a health committee certifying or assessing disability, or from another competent authority that continues to exercise its responsibilities under the law, in the case of persons with a disability (PWD) with a disability rating of at least 67%,
  • an income tax return (E1), in the case of a single-parent family,
  • a Certificate of Large Family Status bearing the digital signature of the Supreme Confederation of Large Families of Greece (ASPE), in the case of a large family.

The funding application serves as:

  • a solemn declaration under Law No. 1599/1986 (Government Gazette A΄75) regarding the information declared, and 
  • an application and consent to retrieve, transmit and cross-check information about the Applicant and their family members against information held by other public-sector agencies and electronic registers. 

For this purpose, before the funding application is submitted, the beneficiary must be notified of and expressly accept all terms and conditions. Applications that have been submitted cannot be corrected.

As part of the Programme, the following online services will be used, as applicable:

online services:

  1. User Authentication Online Service using TAXISnet credentials (passwords), through the Interoperability Center (KED) of the Ministry of Digital Governance.

  2. Online Service for electricity supply details of DEDDIE, from which the following information is retrieved and cross-checked:

  • the electricity supply number at which the station will be installed,

  • the address corresponding to the above supply number,

  • supply characteristics 

The above data processing is carried out by DEDDIE and KED as necessary for the performance of a contract to which the data subject is a party, or in order to take steps at the request of the data subject prior to entering into a contract (Article 6 paragraph 1b GDPR), and for the performance of a task carried out in the public interest entrusted to DEDDIE (Article 6 paragraph 1e GDPR), where public interest means the proper, safe, efficient, smooth and reliable operation of the HEDNO network.

When an application is submitted, data are retrieved and cross-checked through the online services referred to in the previous paragraph. 

If:
  1. it is not possible to cross-check and verify the information required to assess an application, or 
  2. the retrieved information confirms that the application is ineligible, 
the application cannot be submitted successfully or forwarded for assessment.

If the available public expenditure is exhausted while an application is being submitted, the application cannot be submitted.


6.3 Checking completeness and approving funding applications

After the application has been submitted successfully, DEDDIE S.A. carries out an automated check of the supporting documents provided by the applicant to verify their completeness and, provided the participation requirements are met, informs the applicant whether or not they are preliminarily eligible for a grant. If the applicant is deemed preliminarily eligible, the corresponding grant amount is also reserved at the same time. This amount is calculated based on the capacity of the PV station and the capacity of the storage system (if applicable) submitted  by the applicant, in accordance with the expenditure limits and taking into account the additional percentage (10%) for the special cases described in paragraph 3.4 (persons with disabilities, single-parent or large families).

All applications submitted successfully are included among the applications eligible for a grant in the relevant category. 

The approved grant amount for submitted applications cannot be increased.

If the available public expenditure for the category is exhausted during the check and approval process,  the application is rejected.


6.4  Programme implementation period – Milestones 

Programme launch

The exact date and time when applications for the Programme can be submitted will be included in the final Guide. 

Application period 

Applicants may submit grant applications from the Programme launch date until all funds in each category have been allocated.  

Deadline for station implementation

The deadline for station implementation is determined based on the Connection Agreement entered into by the self-consumer with DEDDIE.


7. Certification of the subsidized station – Payment of the Grant

7.1 Required Supporting Documents

To ensure an adequate audit trail and payment of the grant to beneficiaries, the Programme Management and Implementation Body must collect the following supporting documents:

  1. Photocopies of retail transaction documents (e.g., including photocopies of retail sales receipts/sales invoices for the cost of the subsidized equipment/materials and service receipts/service invoices for the relevant installation work, design and supervision).

  2. CE certificates and technical data sheets for the system’s main equipment (photovoltaic system and battery). In particular, for the battery (if applicable), the beneficiary must also provide certificates demonstrating that the batteries comply with IEC 62619 or VDE 2510-50 or UN38.3 or equivalent standards. 

  3. Photocopies of bank transaction documents (e.g. a deposit slip into the beneficiary’s bank account, proof of an executed electronic payment, or proof of payment by debit/credit card), showing settlement of the amount paid by the beneficiary, if required, and payment of any own contribution due to exceeding the maximum grant limits in section 3.4 or due to ineligible expenses.

  4. A statutory declaration by the project beneficiary stating that the equipment used is new and unused, together with a detailed list of the Serial Numbers of the materials used.

  5. A copy of the certificate confirming completion of the connection to ΔΕΔΔΗΕ.

Please note that:

  • photocopies of the retail transaction documents issued (e.g. retail sales receipts, service provision receipts) must bear a signature and a stamp,expenses may not be paid in cash.


7.2 Grant Certification and Payment Procedure

The certification process is carried out by Δ.Ε.Δ.Δ.Η.Ε Α.Ε and includes:

  1. Checking the accuracy of the required supporting documents submitted with the application, as described in section 6.2.

  2. Checking the completeness and accuracy of the required supporting documents, as described in section 7.1.

  3. Checking that no public aid has been received from any other funding programme, in cooperation with the Executive Structure, Energy Sector.

  4. Contacting the beneficiary to address any missing supporting documents.

  5. Certifying the amount payable under the Programme and issuing the Grant Payment Form in accordance with the relevant template.

  6. The grant is paid:

a) to the beneficiaries, if they have paid the expense, and/or

b) to the contractors/suppliers, in the case of an invoice issued on credit. 

  1. Contacting the beneficiary to request an authorisation, in accordance with the relevant template, so that the grant can be paid to the contractors/suppliers. 


 7.3 Issuing documents 

For the design, procurement and construction of a photovoltaic station and storage system  (if applicable), the documents required by current legislation are issued, in particular Law No. 4308/2014 (Government Gazette A' 251/24.11.2014), as amended from time to time. In this context, the following documents, among others, are accepted:

  • A Retail Sales Receipt or an equivalent document under the Greek Accounting Standards (ΕΛΠ) for eligible expenses, made out in the beneficiary’s name. The document must include the following details:

- the beneficiary’s details, date of issue and delivery address, which must match the address of the electricity supply and the eligible installation,

  • the cost of each eligible expense [detailed description of the item, technical specifications of the equipment, quantity, unit price and value].

Please note that: 

  • if the above details cannot be included on the document (e.g. a till receipt), the Supplier/Contractor must provide a statutory declaration stating those details.

  • if the expense documents include details of the recipient’s occupation, then, in the case of a natural person (household), the description “private individual” must be stated, and in in the case of Category D (Farmers), the indication “farmer”.


8. Beneficiary obligations

A beneficiary enrolled in this Program is required to: 

A) comply with the terms of this Program, the connection agreement, and the provisions of national and EU law. 

B) provide any information that may be necessary in relation to the project to HEDNO S.A., by providing specific details. 

C) accept scheduled on-site inspections by the Program Management and Implementation Body, as well as by other competent national or EU audit bodies, following prior consultation, facilitate their work, and provide any information relating to the implementation of the project, if requested. 

D) retain the subsidized equipment for at least five (5) years after the subsidy is paid. 

E) maintain and update the project file with all information relating to the development and construction of the photovoltaic station and the storage system (if applicable), as well as other expenses, through to their completion and payment. The beneficiary must retain all original supporting documents for project expenses throughout the project and for a further five (5) years after the subsidy is paid.


9. Consequences of failure to meet obligations 

If, at any stage of the Program or after its completion, inspections carried out by the competent national or EU bodies establish that beneficiaries have failed to meet their obligations, the Program Management and Implementation Body shall take the necessary measures:

  • to amend the original approval decision and revoke the relevant funding applications,

  • to make a financial correction and recover the aid through the competent Authorities, or adjust it, where required.


The amounts to be recovered are charged to the beneficiaries, who are the final recipients of the aid (where the findings relate to their own non-compliance).


Beneficiaries may, where applicable, appeal the above revocation decision as follows:

  • If the decision does not involve a financial correction:

  • the appeal must be submitted to the Program Management and Implementation Body within thirty (30) days of notification of the audit findings

  • the appeal shall be examined by the Program Management and Implementation Body, both as to the legality of the act and its substantive merits, within sixty (60) days of the appeal being submitted

  • If the decision involves a financial correction and an obligation to repay the aid:

    • the appeal must be submitted in writing to HEDNO S.A., as part of the procedure for issuing a financial correction decision by the competent service of the Ministry of Environment and Energy, within thirty (30) days of notification of the audit findings.

  • the appeal shall be examined by HEDNO S.A. both as to the legality of the act and the merits of the case. The decision on the appeal shall be issued by the competent service of the Ministry of Environment and Energy within sixty (60) days of the appeal being submitted.


10. Publicity and information activities

The Implementing Body must take the necessary publicity measures in accordance with the applicable institutional framework. Interested parties may also obtain information from the Program’s official online portal. 

In all cases, the provisions of Regulation (EU) 241/2021 and Article 6 of Decision No. 119126 EX 2021/28.09.2021 (Government Gazette B’ 4498), issued by the Alternate Minister of Finance, “Management and Control System for the Actions and Projects of the Recovery and Resilience Fund,” concerning information, communication and publicity must be observed.

Interested parties can also find information at: 

  • On the Program’s official online portal (https://pvstegi.gov.gr/) 

  • on the online portal of the Ministry of Environment and Energy (www.ypen.gov.gr) 

  • on the website of the Program’s Management and Implementation body - ΔΕΔΔΗΕ (www.deddie.gr)   

Any type of advertising (e.g. television, radio, printed materials, special promotional activity) relating to the “Photovoltaics on the Roof” Program, by all parties involved in the initiative (e.g. beneficiaries, contractors, suppliers, manufacturers, etc.), must comply with the Program’s publicity requirements, as published on the official online portal.


11. Protection of personal data 

For the purposes of implementing this, ΔΕΔΔΗΕ S.A. acts in the capacity of Data Controller in accordance with the provisions of the General Data Protection Regulation, while the Ministry of Energy and Environment acts in the capacity of Data Processor, as it provides the environment (cloud) in which application data will be stored. Both are required to comply with all obligations arising from the General Data Protection Regulation (EU) 2016/679 of the European Parliament and of the Council of 27 April 2016 (GDPR), as well as the provisions of Law 4624/2019 (Government Gazette A’ 137), in accordance with their respective capacities.

The Ministry of Energy and Environment, as the “Data Processor,” will process personal data on behalf of ΔΕΔΔΗΕ, which acts as the “Data Controller” of the personal data in question, as defined in the  General Data Protection Regulation and national legislation. 

The “Data Processor” will process personal data on behalf of ΔΕΔΔΗΕ to the extent deemed necessary to provide its services, in accordance with the terms of this “Photovoltaics on the Roof” Program.