Roof waterproofing and photovoltaics: Which should be done first?

Planning solar panels on your rooftop? Find out when waterproofing should come first and what to agree on regarding mounting systems, drainage, and coordination of the work.

Roof waterproofing and photovoltaics: Which should be done first?

If you’re planning to install solar panels and are also considering waterproofing your roof terrace, the right sequence starts before the first contractor arrives. Begin with a joint assessment and plan; any necessary work on the roof must be completed before the area is covered with panels. However, the mounting points and cable penetrations need to be agreed on from the outset.

Not every roof terrace needs new waterproofing before solar panels can be installed. You need to know its condition, what work is required and how it will be protected once the system is installed.

First, clarify what you mean by “insulation”

The word “insulation” is often used to refer to two different types of work. Thermal insulation limits heat transfer, while waterproofing prevents water from getting in. They can be parts of the same structure, but neither replaces the other.

If you’re requesting a quote for “insulation and solar panels,” clarify which layers are already in place and what is going to change. The choice of mounting system needs to take the entire roof build-up into account, not just the visible surface.

When should repairs or new waterproofing come first?

Request an on-site assessment before finalizing the panel layout, especially if you’ve noticed dampness on the top floor, recurring repairs or surface damage. Gather previous quotes, photos, material details and any documents covering the earlier work.

During the assessment, you need a clear answer: can the existing waterproofing system stay in place, is a localized repair enough, or is more extensive work required? A roof terrace with no visible leaks shouldn’t be assessed solely on whether your ceiling is dry today.

The need to check the roof’s condition and clarify any repairs before installation is also included in the U.S. Department of Energy’s guide to choosing an installer. For your property, the technical decision should be made by the qualified professionals after an on-site assessment.

The practical order of work on an existing roof terrace

A coordinated plan can be organized into the following steps:

  1. Survey the area. The condition of the roof, existing equipment, drainage outlets and access are documented.
  2. Plan together. The engineer, solar installer and waterproofing contractor agree on the layout, mounting system and cable penetrations.
  3. Necessary construction and waterproofing work. The agreed repairs are carried out, and the details specified in the plan are completed.
  4. Check that the roof is ready. Confirm that the waterproofing system is ready for the next stage of work, in accordance with its manufacturer’s instructions.
  5. Installation and final inspection. The mounting systems and panels are installed with the specified protective measures in place, and the areas where work was carried out are inspected.

This is a coordination sequence, not a technical installation guide. Some mounting details may need to be worked out before the waterproofing is complete. That’s why you should avoid hiring two separate contractors without a shared plan.

Also, don’t rely on a blanket promise that “the panels will go in the next day.” Readiness times depend on the specific material and the application conditions. Ask for this to be included in your project schedule.

Anchored or ballasted mounting systems: What to ask

Ballasted mounting systems use additional weight to hold the installation in place. Anchored systems transfer forces through the specified connections. There are also specialized systems compatible with certain waterproofing membranes, as shown in Sika’s technical presentation on solar rooftops.

The absence of drilling alone doesn’t mean a solution is suitable. Additional loads, wind forces and compatibility with your structure all need to be checked. Where weights are used, the plan must specify how they will be distributed and how the surface supporting them will be protected.

Ask exactly which solution is planned for your roof terrace, who will provide the supporting documentation and who will approve the details where the system meets the waterproofing. Protective layers and fixing points need specific specifications, not on-site improvisation.

Leave room for water and maintenance

Ask for a plan showing access routes, drainage outlets and the points that will need inspection. The value of a roof terrace isn’t determined only by how many panels will fit.

Mounting systems and wiring shouldn’t make it difficult to inspect drainage outlets or get in the way of maintenance. The DOE’s technical guidance on protecting solar panels from weather hazards highlights both problems caused by blocked drainage outlets and damage to membranes from contact with equipment.

Agree on how future access will be provided without putting unnecessary strain on the surface. Don’t try to move panels, mounting systems or cables yourself to reach something point.

An illustrative example of coordination

Let’s assume you have an older roof terrace with recurring damp and are planning to install solar panels. If the panels are installed first and you later decide to carry out general waterproofing, additional work may be needed to remove and reinstall the equipment.

With a joint site inspection beforehand, you can consider the necessary repairs and the system layout as part of the same plan. This is a hypothetical example; the scope and cost of the work depend on your property.

What to get in writing before you start

  • Which repairs are included and which contractor is responsible for each task.
  • What mounting system and waterproofing protection have been agreed.
  • Who confirms that the roof is ready before installation.
  • How access to drains and inspection points will be maintained.
  • What photographic documentation you will receive before critical areas are covered.
  • Who to call if damp appears after the work is complete.

If the waterproofing comes with a warranty, notify the provider before any work is carried out and ask for written clarification of the terms. The need to coordinate with the warranty provider is also mentioned in the Bauder roof design guide. You can also read our guide to solar panel warranties.

Plan your roof terrace as a whole